De Ferrers Academy – Classroom Extension

Project Details

  • Electrical and mechanical works to facilitate a new 8 classroom extension.
  • A design and build M&E service was undertaken in-house by C.B.S.
  • The design consisted of: ventilation, ‘wet’ heating system including upgrading of the existing boiler to enable integration of the new areas to be heated, air conditioning to the IT suites, external lighting, lighting to all internal areas, emergency lighting, fire alarm system (L1 Gent), general power requirements, Cat 5 data installation, CCTV, lightning protection and security alarm.
  • The key design features included: drama room scheme, designed to integrate into the refurbishment and requirements to ensure that all services blended  aesthetically.  The pre-installed flush conduit installation was completed off site enabling a faster installation of the services on site, allowing Buchans to achieve the very tight deadline.
  • C.B.S. offered and supported a turn-key services solution to Buchans Special Projects.
M & E Value £185,000
Contract Period 3 Months
Completion September 2010
Client De Ferrers Academy
Main Contractor Buchans Special Projects